GTRIF: Maiden Inferred Mineral Resource Estimate on GDB Prospects. Trend length of identified mineralized roll fronts at GDB prospects increases to 39,614 feet (7.5 miles). Lo Herma Project expands to ~12,000 acres.

04/25/2023

By Steven Ralston, CFA

OTC:GTRIF | ASX:GTR

READ THE FULL GTRIF RESEARCH REPORT

GTI Energy Ltd (OTC:GTRIF) (ASX:GTR) is a mineral exploration company fully focused on acquiring and advancing U.S.-based uranium assets. Management has advanced its Great Divide Basin Project through two significant drilling campaigns (totaling over 113,000 feet), which has supported a maiden Mineral Inferred Resource Estimate. In addition, the company has staked additional lode claims totaling approximately 12,000 acres in Wyoming’s Powder River Basin, which has been dubbed the Lo Herma Project, which encompasses approximately 12,000 acres. The projected supply/demand imbalance in the upcoming years should drive uranium prices higher. The development and reactivation of U.S. uranium mines are particularly attractive given the initiatives to secure domestic supply for U.S. nuclear reactors.

OUTLINE OF 2022 & 2023 ADVANCEMENTS

Recap of 2022

• In March 2022, the two mud rotary drill rig 100-drill hole (~15,000m or 49,200 ft) exploration campaign at the Thor ISR Uranium Project (that had commenced in November 2021) was completed.

o The campaign discovered 17,640 feet of mineralized roll front trends.

• Between August and December 2022, drill programs (64,220 ft or 19,570m) in several of the company’s GDB properties were completed

o a follow-up drilling program at the Thor prospect discovered an additional 7,974 feet (1.39 miles) of mineralized roll front trends

o initial exploratory drill programs at the Odin, Teebo and Loki prospects that discovered projected roll trends totaling 14,000 feet (2.65 miles)

o In total, the drilling campaign discovered an additional 21,974 feet (4.16 miles or 6,700m) of projected uranium mineralized roll front trends

• To-date, a total of 39,614 feet (7.5 miles) of mineralized roll front trends have been discovered on the GDB properties.

Accomplishments Thus Far During 2023

• In February, GTI Energy secured approximately 8,000 acres (~3,500 hectares) of unpatented mineral lode claims by staking. The claims are now known as the Lo Herma Project and are situated in Wyoming’s Powder River Basin Uranium District. In April, the size of the Lo Herma Project increased to approximately 12,000 acres.

• In mid-March 2023, GTI acquired an historical data package, including logs on 1,445 drill holes (~530,000 ft) that pertain to the Lo Herma Project. Management believes that the historical data is sufficient to prepare an Inferred Mineral Resource Estimate (JORC 2012) (without further drilling) by mid-year.

• In April, GTI Energy delivered a Maiden Inferred Mineral Resource Estimate (MRE) based on In-Situ Recovery (ISR) mining methods and utilizing a cut-off grade of 200 ppm U308 and a minimum grade thickness (GT) of 0.2 per mineralized horizon. The Inferred Resource estimate totals 1.32Mt at an average grade of 570 ppm U308 for 1.66 Mlb. U308.

• A proposed airborne geophysical survey is expected to commence shortly. Terraquest Ltd has been contracted to conducted the survey.

GTI Energy is targeting historically identified mineralized redox roll front trends on the company’s properties in Wyoming, the leading U.S. state for production of uranium by ISR mining. Management’s goal is to define 20 million lbs. of ISR-amenable uranium in the Great Divide Basin, roughly 10 Mlbs across the GDB (Great Divide Basin) properties and 10 Mlbs at the newly staked Lo Herma Project.

DETAILS OF RECENT ADVANCEMENTS

100-hole Exploration Campaign (November 2021 - March 2022)

The objective of the 2021-2022 100-hole (~49,200 ft) work program, which was completed in March 2022, was to identify redox (reduction-oxidation) boundaries and potential host sands at the Thor prospect. Additionally, the program included defining the depth, thickness, grade and width of uranium mineralization across the redox fronts. Management is focused on targeting sandstone-hosted typical of economically viable ISR deposits, namely widths over 50 feet (15m), grades greater than 0.02% (200 ppm) U308, GT (Grade x Thickness) over 0.2 and at a depth of 50 feet (15m) or more below the water table.

103-hole Drilling Campaign at GDB Project (August-December 2022)

The objectives of the 2022 103-hole (64,220 ft) work campaign were to expand the exploration to an area in the northeast part of the Thor Property (including the previously unexplored leases in State Section 29 and 20) through a follow-up drill program and also to conduct initial exploratory drill programs at the Odin, Teebo and Loki prospects. The follow-up program at Thor consisted of 70 holes (34,010 ft. or 10,366m) and 33 holes (30,210 ft. or 9,208m) combined were drilled at Odin, Teebo and Loki.

Follow-up Drilling at Thor

In August 2022, GTI Energy Ltd embarked on a follow-up drilling program at the Thor prospect. Utilizing two mud rotary drill rigs, the program resulted in the discovery of an additional 7,974 feet (1.51 miles) of mineralized roll front trends, increasing current total to 25,614 feet (4.85 miles). These new discoveries consisted of three separate roll fronts, which consist of a main sand unit and two other sand units positioned above (upper sands) and below (lower sands) the main unit. The upper sands added 1,866 feet of additional 7,974 feet while the lower sands contributed 1,201 feet to the projected mineralized roll front trend length.

New Mineralized Roll Front Trend Encountered (on Section 29 State Lease)

Drilling on the previously unexplored State Lease property at the Thor Project discovered 1.39 miles of new roll front trends. Interpretation of the drilling results also projects that mineralization trends extend around 830 feet in both the upper and lower sand units adding a total of an additional 1,667 feet of mineralized roll fronts in these complexes. These role fronts encountered within Section 29 increases the potential that the sands at the Thor Project host an economic ISR deposit.

Initial drilling at Odin, Teebo and Loki

The initial drilling at Odin (18 holes), Teebo (10 holes) and Loki (5 holes) explored approximately five miles of interpreted mineralized roll front trends based on historic information. The number of mud rotary rigs increased to four. Uranium mineralization below the water table was encountered in host sands at all three prospects. In general, mineralization was encountered in multiple sandstone units in geological and hydrogeological settings that appear to be conducive to ISR recovery.

The drilling results confirmed the presence of approximately 14,000 feet of mineralized roll front trends over these three prospects: approximately 4,200 feet at Odin 6,800 feet at Teebo and 3,000 feet at Loki. In addition, correlating the data from historical drill hole maps with the current drilling results, management is projecting that approximately 37,000 feet of roll new front trends should exist across the Odin, Teebo, and Loki claims.

Maiden Inferred Mineral Resource Estimate (Thor and Teebo)

On April 5, 2023, GTI delivered a Maiden Inferred Mineral Resource Estimate (JORC 2012) for the Thor and Teebo prospects based on In-Situ Recovery (ISR) mining methods and utilizing a cut-off grade of 200 ppm U308 and a minimum grade thickness (GT) of 0.2 per mineralized horizon. The Inferred Resource estimate totals 1.32Mt at an average grade of 570 ppm U308 for 1.66 Mlb. U308.

It is important to note that the Inferred Mineral Resource estimate is based on limited areas where drill data and an historical hydrologic study (conducted by Kerr-McGee in 1983) support the criteria necessary to estimate an inferred mineral resource. Thus far, only five of the 10 mineralized sand horizons identified in the Battle Spring formation at South Thor, North Thor and the State Lease were utilized define the estimate.

Exploration Target Range Estimate (GDB Prospects)

Utilizing the results of the drilling programs conducted by GTI Energy and Kerr-McGee’s historical drill hole intercept maps, along with interpretations of redox trend lengths and general characteristic dimensions and grade parameters of sand horizons, the exercise in estimating the mineralization at the Great Divide Basin prospects produced an exploration target range of 6.55 to 8.11 million tonnes with a grade range of 420 to 530 ppm U308, which would contain an estimated 6.10 to 9.53 Mlb. U308. This exploration target range is conceptual in nature and not JORC-compliant.

The Lo Herma Project

GTI Energy has been staking claims in Wyoming’s Powder River Basin since mid-2022, which subsequently were dubbed the Lo Herma Project. Initially, in late September 2022, GTI Energy announced that the company staked and secured 184 lode claims (3,801 acres), which was followed up by an announcement on February 21, 2023, when GTI Energy announced that the number of staked unpatented mineral lode claims had increased to about 8,000 acres (~3,500 hectares). Most recently, on March 14, 2023, GTI announced that the Lo Herma Project had been expanded by staking an additional 4,000 acres, apparently influenced by examining the data of historical drilling (see below). Currently, the Lo Herma Project encompasses approximately 12,000 acres.

Several significant ISR uranium deposits are located in the Powder River Basin including the Irigaray and Christensen Ranch Projects (Uranium Energy Corp - NYSE:UEC), the Smith Ranch-Highland Project (Cameco - NYSE:CCJ) and the Nichols Ranch Project (Energy Fuels - NYSE:UUUU). Lo Herma situated within 10 miles of Cameco’s Smith Ranch-Highland Project, which is the largest ISR uranium production site in Wyoming.

Later in mid-March 2023, GTI Energy announced that it secured a historical (1970’s) data package of drilling logs, downhole geophysical and lithological logs, drill maps and a ground water hydrology report. The package includes paper drill logs on 1,445 drill holes (~530,000 ft) pertaining to the Lo Herma Project. The drill logs indicate that the uranium mineralization with economic potential is hosted by the Fort Union formation, the same formation being ISR-mined by the nearby Smith Ranch-Hyland operation. Management estimates the drilling data has an estimated replacement value of $15 million. The data package was acquired for US$950,000.

Management believes that the historical data is sufficient to prepare a JORC (2012)-compliant Inferred Mineral Resource Estimate without further drilling. Management expects the MRE to be completed (with qualifications) by mid-year, setting stage for verification drilling during the summer.

The drill data is being digitized into a database in order to 1) convert the data so that the eU308 grades can be better understood and 2) correlate the geophysical logs with the lithological information to help determine the mineralized horizons. After interpreting the results, management plans to conduct a field and drill verification programs in the future.

Placement to Support the Lo Herma Project

To help fund the Lo Herma Project (data package acquisition, development and exploration) GTI conducted a placement of 260,000,000 shares at a price of $0.009 per share. Gross proceeds of the placement were $2,340,000. Included with the placement was one free attached listed GTRO option exercisable at $0.03 until October 20, 2024 that was issued for every two shares subscribed. 130,000,000 Placement options were issued.

Exploration Target Range Estimate (Lo Herma Project)

After a desktop review of the Lo Herma historical data package, an exploration target range was prepared in order to provide an initial assessment of Lo Herma’s potential. Utilizing the drilling data, maps and drill hole gamma logs, mineralization hosted in certain sandstone horizons in the Wasatch formation was estimated along redox trends using average grades and dimensions derived from drill hole maps. The deeper sands of the Fort Union formation were omitted since there was the data package did not contain any information regarding sand horizons below 400 feet. The exercise produced an exploration target range of 7.31 to 9.02 million tonnes with a grade range of 500 to 700 ppm U308, which would contain an estimated 8.05 to 13.92 Mlb. U308. This exploration target range is conceptual in nature and not JORC-compliant.

New Claims Staked at Thor Property

As part of the company’s April 5th press release, GTI Energy announced that roughly 250 acres of additional lode claims had been staked at the Thor Project. The new claims were staked based on the data from the company’s drilling campaigns that identified mineralized roll front trends and are situated as interpreted extensions of those trends. Specifically, the newly staked claims are directly adjacent to the east of existing Thor claims and to the south of the State Sections. The company relinquished some claims (~600 hectares), ~450 hectares at the western end of Thor and ~150 hectares on the eastern end of Loki West.

Upcoming Airborne Geophysical Survey at the Green Mountain Project

GTI Energy is planning an airborne geophysical survey for the Green Mountain Project. Terraquest Ltd has been contracted to conducted the survey, which is expected to be conducted during April 2023, weather permitting. The survey is designed to capture radiometric, magnetic and electro-magnetic data, which will be correlated with historical drilling data in an effort to define exploratory drill targets. The high priority targets are expected to be drilled during the second half of 2023.

Valuation

The P/B valuation range of ISR companies with U.S. uranium projects is between 1.35 and 3.69. With the expectation that GTI Energy’s stock (OTC:GTRIF) will attain an industry average P/B ratio of 2.29, our comparable analysis valuation price target is US$0.024.

SUBSCRIBE TO ZACKS SMALL CAP RESEARCH to receive our articles and reports emailed directly to you each morning. Please visit our website for additional information on Zacks SCR. 

DISCLOSURE: Zacks SCR has received compensation from the issuer directly, from an investment manager, or from an investor relations consulting firm, engaged by the issuer, for providing research coverage for a period of no less than one year. Research articles, as seen here, are part of the service Zacks SCR provides and Zacks SCR receives quarterly payments totaling a maximum fee of up to $40,000 annually for these services provided to or regarding the issuer. Full Disclaimer HERE.